Colorado Springs Could Gain Second Stop on Colorado’s Front Range Passenger Rail Line Under New Draft Plan

Colorado Springs Could Gain Second Stop on Colorado’s Front Range Passenger Rail Line Under New Draft Plan

Colorado’s proposed Front Range Passenger Rail project continues to take shape, with a newly released draft plan outlining expanded service for southern Colorado. The proposal includes a potential second passenger rail station in north Colorado Springs and increased investment in the region as the state advances plans for a modern intercity rail network.

New Draft Plan Expands Passenger Rail Vision for Colorado Springs

The Front Range Passenger Rail District (FRPR) has released a draft update for the Colorado Connector, known as CoCo, the planned passenger rail service that would connect communities along Colorado’s Front Range.

Among the most significant recommendations is the addition of a possible second station in north Colorado Springs, complementing the city’s planned downtown stop. Officials say the expanded station network is intended to improve access for residents and strengthen regional transportation options.

The proposal also calls for increasing the annual local return to Colorado Springs from approximately $3.5 million to $6.6 million to support rail connectivity and ongoing operations.

CoCo Rail Line Planned to Connect 12 Colorado Cities

Passenger Service Would Link Fort Collins to Pueblo

According to the FRPR, the Colorado Connector is designed as an intercity passenger rail service connecting 12 cities stretching from Fort Collins in northern Colorado to Pueblo in the south.

The project’s name, CoCo, was selected through a public vote that drew participation from more than 25,000 Colorado residents, reflecting broad public interest in expanding passenger rail across the state.

The proposed rail corridor is expected to offer an alternative to driving along the heavily traveled Interstate 25 corridor, improving mobility for commuters, business travelers, and visitors while supporting long-term regional growth.

See also  Amazon relies on electric cars

Construction Timeline Points to Southern Expansion in 2032

Northern Segment Scheduled First

Under the current draft plan, the initial phase of passenger rail service would begin in 2029, focusing on the northern section of the route.

Service to Colorado Springs and Pueblo would follow in 2032, extending the network into southern Colorado as later phases of the project are completed.

The updated plan also includes a formal commitment to begin service in Colorado Springs and Pueblo within five years of securing project funding, providing a clearer timeline for communities awaiting rail expansion.

Downtown Station Could Be Relocated for Better Access

The draft proposal recommends moving the planned downtown Colorado Springs platform to the east side of the railroad tracks. According to the FRPR, the change would improve pedestrian access and create a more convenient connection to the city’s downtown district.

Officials also say the plan places greater emphasis on strengthening access to the downtown areas of both Colorado Springs and Pueblo, aligning future rail service with key commercial and civic centers.

Looking Ahead

While the latest proposal remains in the draft stage, it outlines a broader vision for expanding passenger rail service across Colorado. If approved and funded, the Colorado Connector would provide new transportation options linking communities from Fort Collins to Pueblo, with Colorado Springs positioned to receive enhanced service through an additional station, increased operational funding, and improved downtown accessibility.