Socialpost

Complete News World

Foundation stone laid for new postal logistics center - wien.ORF.at

Foundation stone laid for new postal logistics center – wien.ORF.at

Economie

Austrian Post is pressing ahead with expanding its logistics hubs. The groundbreaking ceremony for the building has now been held in Inzersdorf. The listed company invests 70 million euros, and the entire area covers nearly 23,000 square meters.

The sorting capacity is expected to be 25,500 parcels per hour, and completion is scheduled for August 2023. “The Parcel Logistics Center hall existing since 2002 will be maintained, and will be used primarily for delivery from 2023. It will secure The project has over 1,500 existing jobs and will create over 100 new jobs.”

Austrian Post AG

The new logistics center is scheduled to be completed in August 2023

Home to bees and bats

The landscape architects have developed a “concept of environmentally sustainable green space” for open spaces and rooftop areas in a logistics center, for example, rooftop areas will be greened and equipped with PV modules. The output of the new solar system should be 2 megawatts, and there is already a system in the existing building.

The green space will be planted with native or site-appropriate trees and shrubs, perennials and wildflower seeds, which should captivate with their blooms in spring with plenty of green in summer and provide a natural habitat for many animal species such as wild bees and bats.

See also  St. Polten Hospital: The department scans the ISO again